Showing posts with label Maintenance work. Show all posts
Showing posts with label Maintenance work. Show all posts

Maintenance Works at the El Deposito (2022)

Project: Maintenance Works at the El Deposito (2022)
Location: Pinaglabanan Memorial Shrine, San Juan City
Cultural property owner: National Historical Commission of the Philippines
GAA Budget: P2,000,000.00
Fiscal year: 2022
Date started: 2022
Date completed: June 2022
Implementing agency: National Historical Commission of the Philippines
Contractor: D.M. Celac
Photos:
Interior of the El Deposito underground tunnel, 2021


Maintenance Works at the Miguel Malvar Historical Landmark (2022)

Project: Maintenance Works at the Miguel Malvar Historical Landmark (2022)
Location: Batangas
Cultural property owner: National Historical Commission of the Philippines
GAA Budget: P1,000,000.00
Fiscal year: 2022
Date started: 2022
Date completed: To be determined
Implementing agency: National Historical Commission of the Philippines
Contractor: To be determined

Maintenance Works at the Baldomero Aguinaldo Historical Landmark (2022)

NHCP Photo Collection, 2022

NHCP Photo Collection, 2022
Project: Maintenance Works at the Baldomero Aguinaldo Historical Landmark (2022)
Location: Binakayan, Kawit, Cavite
Cultural property owner: National Historical Commission of the Philippines
GAA Budget: P1,000,000.00
Fiscal year: 2022
Date started: 2022
Date completed: To be determined
Implementing agency: National Historical Commission of the Philippines
Contractor: To be determined

Maintenance Works at the Rizal Shrine Dapitan (2022)

Project: Maintenance Works at the Rizal Shrine Dapitan (2022)
Location: Dapitan, Zamboanga del Norte
Cultural property owner: National Historical Commission of the Philippines
GAA Budget: P2,000,000.00
Fiscal year: 2022
Date started: 2022
Date completed: To be determined
Implementing agency: National Historical Commission of the Philippines
Contractor: To be determined

Maintenance Works at the Casa Real Shrine (2022)

Project: Maintenance Works at the Casa Real Shrine (2022)
Location: Malolos, Bulacan
Cultural property owner: National Historical Commission of the Philippines
GAA Budget: P1,000,000.00
Fiscal year: 2022
Date started: 2022
Date completed: To be determined
Implementing agency: National Historical Commission of the Philippines
Contractor: To be determined

Maintenance Works at the Ramon Magsaysay Historical Landmark (2022)

Project: Maintenance Works at the Ramon Magsaysay Historical Landmark (2022)
Location: Castillejos, Zambales
Cultural property owner: National Historical Commission of the Philippines
GAA Budget: P1,000,000.00
Fiscal year: 2022
Date started: 2022
Date completed: To be determined
Implementing agency: National Historical Commission of the Philippines
Contractor: To be determined

Repair and Rehabilitation of Museo ni Mabini sa Tanauan

Project: Repair and Rehabilitation of Museo ni Mabini sa Tanauan
Location: Tanauan, Batangas
Cultural property owner: National Historical Commission of the Philippines
GAA Budget: P12,000,000.00
Fiscal year: 2019
Project duration: 240 calendar days
Date started: Not yet started
Target date of completion: To be determined
Implementing agency: National Historical Commission of the Philippines
Contractor: R.A. Lacanlale Const.
Project description:

The project aims to restructure the roof trusses and ceiling of the main building. In addition, an overall rehabilitation of the wiring system of the museum complex is included in the scope of the project.

Scope of the project:

1.0        MOBILIZATION AND SITE PREPARATION;

1.1.       Photo documentation (before, during and after);
1.2.       Temporary facility w/ electrical and water consumption;
1.3.       Rental/provision of scaffoldings and board-up;

1.4.       Construction safety and health requirements;
1.4.1.    Provision of personal protective equipment;
1.4.2.    Cordoning and fencing works;
1.4.3.    Construction signage;
1.4.4.    Installation of dropnets;

1.5.       Preparation of as-built plans (signed and sealed);

2.0        ROOFING WORK

2.1.       Provision of new roofing and roofing system (museum and e-learning);
2.2.       Waterproofing work of canopy (courtyard);

3.0        CEILING WORKS

3.1.       Repair of damaged acoustic boards at ground floor (museum);
3.2.       Provision of new ceiling system at second floor (museum), e-learning and canopy;

4.0        DOORS AND WINDOWS

4.1.       Repair, rehabilitation, and refinishing of doors and windows;
4.2.       Provision of tinting for all reflective glass windows;
4.3.       Provision of window ledge (courtyard);

5.0        TILE WORK

5.1.       Replacement of tiles at the museum;
5.2.       Repair and rehabilitation of tomb;

6.0        PAINTING WORK

6.1.       Surface preparation;
6.2.       Museum, e-learning, public toilet, guard house, tomb, perimeter fence and path walk roofing;

7.0        ELECTRICAL WORK

7.1.       Replacement of panel boards (museum);
7.2.       Rewiring and repair of damaged lighting fixtures (museum and e-learning);
7.3.       Provision of emergency light (museum);
7.4.       Rehabilitation of air-conditioning ducting and cables at stereoscopy room, gallery 5 and 6;
7.5.       Provision of projector at conference room;
7.6.       Replacement and rewiring of all convenience outlet (museum and e-learning);
7.7.       Transfer of main feeder line to main distribution panel (e-learning and tomb);
7.8.       Site Electrical Work
7.8.1.    Provision of new lamp posts;
7.8.2.    Provision of bollards;

8.0        PLUMBING WORK

8.1.       Repair of plumbing system at male and female restrooms (museum);

9.0        SITE DEVELOPMENT WORK

9.1.       Rehabilitation of tank house and PWD ramp;
9.2.       Provision of cobble stone path walk;

10.0      REPAIR AND REHABILITATION OF EXISTING ”BAHAY KUBO”;

11.0      CLEARING AND CLEANING OF SITE



Project documentation:

The site of the Museo ni Mabini sa Tanauan

Replica of Mabini's bahay kubo

The tomb of Apolinario Mabini designed by Juan Nakpil

Rehabilitation of Rizal Shrine Dapitan (Phase 2)

Project: Rehabilitation of Rizal Shrine Dapitan
Location: Dapitan City
Cultural property owner: National Historical Commission of the Philippines
GAA Budget: P40,000,000.00
Fiscal year: 2016
Date started:
Date completed:
Implementing agency: National Historical Commission of the Philippines
Contractor: J.S. Lim Construction and Trading

Project description:

The rehabilitation work was part of the NHCP's program on the modernization of its history museums nationwide. This second phase of the project mainly focused on site improvement and stabilization of the retaining walls of the area covering the shrine.



Rehabilitation of Pres. Ramon Magsaysay House

Project: Rehabilitation of Pres. Ramon Magsaysay House
Location: Castillejos, Zambales
Cultural property owner: National Historical Commission of the Philippines
GAA Budget: P10,000,000.00
Fiscal year: 2016
Date started:
Date completed:
Implementing agency: National Historical Commission of the Philippines
Contractor:
Project description: The rehabilitation work was part of the NHCP's program on the modernization of its history museums nationwide.

Repair and partial restoration of the Old City Hall Building of San Pablo

Project: Repair and partial restoration of the Old City Hall Building of San Pablo
Location: San Pablo City, Laguna
Cultural property owner: City Government of San Pablo
GAA Budget: P20,000,000.00
Fiscal year: 2018
Date started: 25 August 2018
Target date of completion: 25 January 2019
Implementing agency: National Historical Commission of the Philippine
Contractor: R.A. Lacanlale Const.
Project documentation:

The old city hall prior to its restoration (21 May 2018)

Perspective drawing of the old city hall

Facade of the old city hall (21 May 2018)

Restoration of Pavia Church

Project: Restoration of Pavia Church
Location: Sta. Monica Parish, Pavia, Iloilo
Cultural property owner: Archdiocese of Jaro
GAA Budget: P10,000,000.00
Fiscal year: 2017
Implementing agency: National Historical Commission of the Philippines
Contractor: J.S. Lim Construction and Trading
Project description:
The project included the restoration/repair of the exterior walls and the rehabilitation of the interior spaces.
Photos:
Cleaning, pointing/re-pointing, and stabilization of the walls at the church facade.

Rehabilitation work at the interior of the church
The completed rehabilitation of the interior of the church

Rehabiltation work at the interior of the church
The completed rehabilitation of the interior of the church