Restoration of Barcelona Church (Phase 2)

Project: Restoration of Barcelona Church (Phase 2)
Location: Barcelona, Sorsogon
Cultural property owner: Diocese of Sorsogon
GAA Budget: P40,000,000.00
Fiscal year: 2019
Date started: No data
Date completed: 2020
Implementing agency: National Historical Commission of the Philippine
Contractor: R.A. Lacanlale Const.
Project description:

This second phase of the project will include the restoration of the coral walls and all architectural finishes of the building including a reproduction of a Baroque style retablo and ceiling paintings.

Scope of the project:

I.    MOBILIZATION AND SITE PREPARATION

I.1.    Photo documentation (before, during, and after) of the project;
I.2.    Field office;
I.3.    Storage for dismantled materials;
I.4.    Electrical and water consumption;
I.5.    Rental of scaffolding;
I.6.    Construction safety and signages;
I.7.    Installation of drop nets;
I.8.    Safety and health requirements;
I.9.    Preparation of as-built plans;

II.    RESTORATION/REHABILITATION WORK

II.1.    Restoration of stone and masonry walls;
II.1.1.    Mechanical cleaning – vegetation removal
II.1.2.    Chemical cleaning – herbicide and biocide application
II.1.3.    Chipping of cement plaster, wall tile cladding and paint

II.2.    Restoration and consolidation of unreinforced masonry walls;
II.2.1.    Stabilization of rubble core;
II.2.2.    Consolidation of cracks on walls;
II.2.3.    Provision and re-installation of lost/missing coral blocks, finials, cornices, moldings and ornaments;
II.2.4.    Re-pointing of masonry joints and gaps;
II.2.5.    Lime plastering of coral stone walls;
II.2.6.    Application of damp proofing/ water repellent solution on masonry walls;

II.3.    Restoration of side Eucharistic adoration chapel
II.3.1.    Tile work;
II.3.2.    Ceiling work;
II.3.3.    Additional wall;

III.    PROVISION OF CONCRETE RETABLO, RETABLO FOR ADORATION CHAPEL AND CONCRETE RELIEF

IV.    PROVISION OF CHOIR LOFT AND COMMUNION RAIL

V.    DOORS AND WINDOWS
V.1.    Dismantling of existing grille windows;
V.2.    Provision and installation of grilles;
V.3.    Provision of wooden awning windows w/ stained glass;
V.4.    Provision and installation of doors;

VI.    ARCHITECTURAL WORKS

VII.    CEILING WORKS

VIII.    TILE WORK

VIII.1.    Dismantling of existing floor tiles concreting w/ surface preparation;
VIII.2.    Chipping of existing nave and altar tiles;
VIII.3.    Provision and installation of nave and altar tiles;

IX.    CLADDING OF NEW COLUMNS

X.    SITE WORK

X.1.    Provision of church drainage system /trench drain
X.2.    Provision of concrete road
X.3.    Provision of concrete pathwalk w/ bomanite finish
X.4.    Provision of grass, plants w/ garden soil
X.5.    Provision of perimeter fence
X.6.    Rehabilitation of Risen Christ Monument
X.7.    Provision of low wall


XI.    ELECTRICAL WORK

XI.1.    General electrical re-wiring
XI.2.    Provision of sound reinforcement system

XII.    PROVISION AND INSTALLTION OF CHURCH FURNISHING

XIII.    CONCEPTUALIZATION, DESIGN, FABRICATION AND PRODUCTION OF CEILING PAINTING, DECORATIVE FINISHES (RETABLOS, ALTAR TABLE, LECTERN), AND BAPTISTRY PAINTING

XIV.    CLEARING, CLEANING AND HAULING

Project documentation:

Drone documentation of the church, including the facade.