Project: Conservation of Bato Church (Phase 1)
Location: St. John the Baptist Parish, Bato, Catanduanes
Cultural property owner: Diocese of Virac
GAA Budget: P9,940,000.00
Fiscal year: 2018
Date started: 26 July 2018
Target completion date: 21 February 2019
Implementing agency: National Historical Commission of the Philippines
Contractor: R.A. Lacanlale Const.
Project documentation:
 |
| The facade before the restoration work |
 |
| Ongoing restoration work (September 2018) |
 |
| Before restoration |
 |
| Ongoing restoration work (September 2018) |
 |
| Before restoration |
 |
| Ongoing restoration work (September 2018) |
 |
| Before restoration |
 |
| Ongoing restoration work (September 2018) |
 |
| Altar area before the restoration |
 |
| Altar area during the restoration work (September 2018) |
 |
| The concrete choir loft before the restoration work. |
 |
| The ongoing dismantling of the concrete choir loft (September 2018) |
 |
| Cleaning, repointing, and consolidation of corals and river stone walls (August 2018) |
 |
| Cleaning, repointing, and consolidation of corals and river stone walls (August 2018) |
 |
| Cleaning, repointing, and consolidation of corals and river stone walls (August 2018) |
 |
| Cleaning, repointing, and consolidation of corals and river stone walls (August 2018) |